Legal Basis
The Building Modernization Act (GModG) defines the requirements for future heating systems. The law explicitly permits the installation of all types of heating systems, including new oil and gas heating systems—but with additional requirements. Existing heating systems may continue to be operated.
The Building Modernization Act (GModG)
The Building Modernization Act replaces the previously applicable Building Energy Act (GEG). The new law, in particular, simplifies the legal requirements for installing new oil and gas heating systems. The most important regulations regarding heating systems are:
- All existing heating systems may continue to be operated
- There is no requirement to replace old or inefficient heating systems
- Connection to a district heating network is possible without restrictions
- The installation of heat pumps is also possible in principle. However, there are guidelines regarding where outdoor units may be installed.
- New oil and gas heating systems must use an increasing proportion of renewable energy sources
- New direct-electric heating systems are permitted only in very well-insulated buildings
Regulations for Heat Pumps
When installing a heat pump, specific requirements must be observed, particularly for outdoor units:
- Noise control and spacing requirements apply to the outdoor unit of an air-source heat pump. If the minimum distances to the nearest building are not maintained, additional noise control measures may be necessary.
- Depending on where you live, front yard or landscaping regulations (opens in a new tab) may apply. These may prohibit the installation of a heat pump outdoors.
- In some cases, historic preservation regulations may prohibit the installation of a heat pump in certain locations.
- If geothermal energy or groundwater is to be used as a heat source, additional approval from the local water protection authority is required. This is generally not permitted in water protection areas.
Regulations for New Oil and Gas Heating Systems
For newly installed oil and gas heating systems, an increasing proportion of the energy must come from renewable sources. This so-called “bio-staircase” provides for the following stages:
| January 1, 2029: | 10 percent |
| January 1, 2030: | 15 percent |
| January 1, 2035: | 30 percent |
| January 1, 2040: | 60 percent |
| January 1, 2045: |
100 percent |
The final stage of the bio-staircase is not explicitly mentioned in the Building Modernization Act. It is to be specified in a separate law by the end of 2026.
This requirement can be met by replacing a corresponding proportion of the fuel with bio-oil or biogas. Alternatively, hydrogen and synthetic fuels produced from hydrogen can also be used here.
Another way to meet this requirement is through hybrid systems. These combine an oil or gas heating system with a more climate-friendly heating system—such as a heat pump or a solar thermal system.
New Rules for Oil and Gas Heating Systems in Rental Apartments
To protect tenants from rising heating costs, new rules apply to newly installed oil and gas heating systems in rental apartments. The rationale is that costs for fossil fuels are expected to rise in the coming years. For this reason, landlords will contribute to a portion of the ongoing costs.
Landlords will cover 50 percent of:
- grid fees for the gas network
- CO₂ costs associated with the fossil fuel portion
- Additional costs for the legally mandated share of renewable energy through 2039. After that, the 50/50 rule no longer applies to the share of biogas or bio-oil. Tenants will pay a higher proportion than landlords: 75 percent starting in 2040 and 85 percent starting in 2045.
Important: This regulation also applies if tenants have entered into their own supply contract for oil or gas. In this case, they can reclaim the portion of the costs that would have been borne by the landlord.
Regulations Governing the Dismantling of the Gas Network
In the long term, the number of customers connected to the natural gas grid will decline. At the European level, regulations have therefore been established for the decommissioning of the gas grid, which are currently being implemented into national law.
The planned amendment to the Energy Industry Act stipulates that natural gas network operators must first develop and publish a decommissioning plan. Connections may then be disconnected no sooner than ten years after publication—even if the affected consumers have not given their consent. The long lead time is intended to ensure that an alternative heating system can be installed well in advance.